From open stud walls to a finished home: insulation, drywall, a double-sided stone fireplace, new windows, kitchen cabinets, flooring, paint and new exterior siding. Here is the whole job, start to finish, in the order it happened.
One home in Sandy, one crew, start to finish. Every photo below is from this job.
The Finished Home
Step 1: Opening Up the Walls and Insulating
December 2025
With the house opened up to the studs, our crew insulated the walls and ceilings throughout before anything else went back together. Getting the insulation right at this stage is what makes the finished home comfortable and efficient for years.
Step 2: Drywall
Late December 2025 to early January 2026
Then we hung, taped and finished drywall on every wall and ceiling in the house, turning bare framing back into real rooms, ready for paint.
Step 3: A Double-Sided Stone Fireplace
January to February 2026
We framed in a double-sided fireplace, built the surround and mantel, and finished it in stone veneer. It became the centerpiece of the main living space.
Step 4: New Windows
Late January to early February 2026
We installed new windows, opening the home up to more light and the mountain views.
Step 5: Kitchen Cabinets and Counters
February 2026
New white shaker cabinets went in next, set level and true, with a floor-to-ceiling pantry wall, a farmhouse sink in the island, new countertops, a tile backsplash and a custom range hood.
Step 6: Flooring and Paint
February 2026
New plank flooring ran through the main living areas, and fresh paint brought every room together, from the kitchen to the fireplace wall.
Step 7: New Exterior Siding
March 2026
To finish the job outside, we wrapped the exterior and installed new dark siding, giving the home a clean, modern look that matches the work inside.
Planning a remodel? Let’s talk.
Licensed and insured. Based in Syracuse, serving Weber and Davis counties and beyond. Call (385) 430-7420 or request a free estimate.